Considering the cost, the efficiency of constructions, the restriction of geological conditions, and other issues, blasting is generally inevitable for excavation in tunnel constructions. The ground vibration induced by blasting may have some negative effects on surrounding structures and neighborhood. Therefore, understanding the impacts of ground vibration induced by blasting is important to tunnel construction.
This study performed a carefully planned field measurement for ground vibration and sound induced by blasting test, the weight of explosive was the equivalent of the latest design in “New Wu-Shan-Ling Headrace Tunnel Project”, so that the influences of this construction can be estimate. The measured data was analyzed to derive the vibration characteristics, including the velocity attenuation relation, Fourier and response spectra. Also, compared measurement results with worldwide vibration criteria.
Because of the careful planning and well organized, large amounts of data have been successfully measured. The data include the vibration at free filed, surrounding structures, slopes and the Wu-Shan-Ling headrace tunnel. From the attenuation relationship between PGV and distances, the coefficient of determinations are very high, shows consistency at both east side and west side of tunnel. Fourier spectral analysis founds that free field near by the blasting area has dominant frequency about 50 Hz, also founds the natural vibration frequency of structures. Response spectrum analysis shows that the blasting has small effect on long-period structures. After the distance is greater than 70 m, the ground vibrations are under worldwide acceptance criteria. |
參考文獻 |
[1] Dowding, C. H., Blast Vibration Monitoring and Control, Prentice-Hall, Inc., NJ (1985).
[2] Siskind, D. E., Stagg, M. S., Kopp, J. W., and Dowding, C.M., “Structure Response and Damage Produced by Ground Vibration from Surface Mine Blasting,” USBM Report 8507 (1980).
[3] Swedish Standard, “Vibration and Shock-Guidance Levels for Blasting-Induced Vibration in Building,” SS 460 48 66, Stockholm, Sweden (1991).
[4] BSI British Standard, “Code of Practice for Noise and Vibration Control on Construction and Open Sites-Part 2: Vibration,” BS 5228-2 (2009).
[5] BSI British Standard, “Guide to Evaluation of Human Exposure to Vibration in Buildings-Part 1: Vibration Sources Other Than Blasting,” BS 6472-1 (2008).
[6] BSI British Standard, “Guide to Evaluation of Human Exposure to Vibration in Buildings-Part 2: Blasting Induced Vibration,” BS 6472-2 (2008).
[7] BSI British Standard, “Mechanical Vibration and Shock-Evaluation of Human Exposure to Whole-Body Vibration- Part 4: Guidelines for the Evaluation of the Effects of Vibration and Rotational Motion on Passenger and Crew Comfort in Fixed –Guideway Transport Systems,” BS 2631-4 (2001).
[8] German Standards Institute, “Structural Vibration Part 3: Effects of Vibration on Structures,” DIN 4150, Part 3 (1996).
[9] Swiss Association of Standardization, “Effects of Vibration on Construction,” Seefeldstrasse9, CH 8008, Zurich, Switzerland (1978).
[10] Kuzu, C., “The mitigation of the vibration effects caused by tunnel blasts in urban areas: a case study in Istanbul,” Environmental Geology, Vol. 54, pp. 1075-1080 (2008).
[11] Ma, G., Hao, H., Zhou, Y., “Assessment of structure damage to blasting induced ground motions,” Engineering Structures, Vol. 22, pp. 1378-1389 (2000).
[12] Nateghi, R., “Evaluation of blast induced ground vibration for minimizing negative effects on surrounding structures,” Soil Dynamics and Earthquake Engineering, Vol. 43, pp. 133-138 (2012).
[13] Ozer, U., Kahriman, A., Aksoy, M., Adiguzel, D., and Karadogan, A., “The analysis of ground vibrations induced by bench blasting at Akyol quarry and practical blasting charts,” Environmental Geology, Vol. 54, pp. 737-743 (2008).
[14] Ozer, U., “Environmental impacts of ground vibration induced by blasting at different rock units on the Kadikoy–Kartal metro tunnel,” Engineering Geology, Vol. 100, pp. 82-90 (2008).
[15] 中華人民共和國國家標準,「爆破安全规程」,GB6722 (2011)。
[16] 行政院環境保護署,噪音管制法規,行政院環境保護署,民國102年8月。
[17] 張瑞麟,「爆破工程之震動」,地工技術,第61期,67-77頁,民國86年6月。
[18] Hagan, T.N.、Mercer, J.K.,「適用於台灣地區地下開挖工程之安全與經濟開炸方式」,中興工程技術研究發展基金會譯印,台北市,民國八十九年。
[19] 「烏山嶺第2隧道可行性規劃:工程地質補充調查及試驗專題」,經濟部水利署規劃試驗所,台中市,民國九十九年。
[20] 黃文等編著,「隧道開炸技術諮詢系統之研究(二)」,交通部台灣區國道新建工程處,台北市,民國八十九年。
[21] 黃俊鴻,「隧道開炸振動對鄰近結構影響之研究」,榮民工程股份有限公司,台北市,民國八十九年。
[22] 黃俊鴻、游騰瑞、葉品毅,「隧道開炸振動環境影響評估與技術準則之研訂期中報告」,中興工程顧問股份有限公司,台北市,民國一百年。
[23] 黃俊鴻、杜東岳,「隧道開炸引致環境振動之量測分析」,中國土木水利工程學刊,第十八卷第三期,337-351頁,民國95年9月。
[24] 杜東岳,「施工地盤振動特性與數值模擬」,博士論文,國立中央大學,2010。
[25] 陳慧珊,「煤灰地盤施打擠壓砂樁之施工振動特性」,碩士論文,國立中央大學,2013。 |