中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/1545
English  |  正體中文  |  简体中文  |  全文笔数/总笔数 : 78728/78728 (100%)
造访人次 : 33548393      在线人数 : 559
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
搜寻范围 查询小技巧:
  • 您可在西文检索词汇前后加上"双引号",以获取较精准的检索结果
  • 若欲以作者姓名搜寻,建议至进阶搜寻限定作者字段,可获得较完整数据
  • 进阶搜寻


    jsp.display-item.identifier=請使用永久網址來引用或連結此文件: http://ir.lib.ncu.edu.tw/handle/987654321/1545


    题名: 電子廠房地上結構物興建工法最佳化之研究;The hi-tech plant of ground structure is research of the construction labor law optimization
    作者: 周明正;Ming-Cheng Chou
    贡献者: 土木工程學系碩士在職專班
    关键词: 預鑄工法;電子廠房;施工規劃;施工動線;整數規劃;數學規劃;construction planning;mathematical programming;precast construction method;hi-tech plant;integer programming;construction route
    日期: 2009-06-31
    上传时间: 2009-09-21 09:31:26 (UTC+8)
    出版者: 國立中央大學圖書館
    摘要: 台灣製造業的重心已從傳統產業轉成高科技產業,而高科技產業廠房規模也越來越大,整體建廠預算從數百億至千億,其中,土建造價約數十億到百億不等。因應高科技電子產品推陳出新或急單需求,快速建廠、縮短工期,也成為建廠過程的重要課題。而縮短工期必定會影響營建成本。 本研究以某電子廠房建廠案例資料,建構快速建廠合理建造費用之整數規劃數學模式。提供施工方案決策時的參考,降低方案規劃所需時間,縮減初期設計規劃時程。 本研究以最佳化理論為基礎,將電子業快速建廠的需求考量,建立相關規劃數據,發展出發包初期決策階段時之施工工法方案建議模式。並對各施工方法的建造金額、施工工期、施工順序、施工動線影響施工總工期及建設總費用等為限制條件,且考量施工方式之合理性,建構出快速建廠合理建造費用之整數規劃數學模式,並運用LINGO 7.0 數學規劃軟體求得。透過範例測試及敏感度分析,以印證本研究最佳解運用之合適性。 Recently, the high-tech industry has taken on an important role for the economic development of Taiwan. The size and complexity of hi-tech plants have increased continuously. Besides, the construction costs have increased to several billions. Due to the continuous compression of life cycles for high-tech products, it becomes an important issue to shorten plant construction as much as possible. To maintained construction quality, short construction time must have a great effect on the construction cost. Based on the optimization theory, this research proposes an interger programming model to account for the relation of construction time and the construction costs. Using the proposed model, the construction time and the costs can be quickly estimated during the preliminary planning stage. In the proposed model, the construction costs, construction time, and construction sequence and access route correspoinding to the different construction method are used as the constraints. Using the linear programming techniques, the best and reasonable construction costs, time, and construction method can be obtained. Sample test and sensitivity analysis are also performed to verify the applicability of the proposed model.
    显示于类别:[土木工程學系碩士在職專班] 博碩士論文

    文件中的档案:

    档案 大小格式浏览次数


    在NCUIR中所有的数据项都受到原著作权保护.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明