English  |  正體中文  |  简体中文  |  全文筆數/總筆數 : 80990/80990 (100%)
造訪人次 : 42120173      線上人數 : 1310
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
搜尋範圍 查詢小技巧:
  • 您可在西文檢索詞彙前後加上"雙引號",以獲取較精準的檢索結果
  • 若欲以作者姓名搜尋,建議至進階搜尋限定作者欄位,可獲得較完整資料
  • 進階搜尋


    請使用永久網址來引用或連結此文件: http://ir.lib.ncu.edu.tw/handle/987654321/64787


    題名: 共同管道施作機具與人力最佳決策模式之研究-以福國路延伸段為例
    作者: 林志昇;lin,Chih-shen
    貢獻者: 土木工程學系在職專班
    關鍵詞: 共同管道;人機作業;機具派遣;最佳化;整數規劃;common channel;man-machine operation;machinery dispatch;optimization;integer programming
    日期: 2014-07-14
    上傳時間: 2014-10-15 14:24:22 (UTC+8)
    出版者: 國立中央大學
    摘要: 摘 要
    一般土木工程人機派遣皆是經驗來派遣,往往是以平均分配較為公平合理性,但熟不知這些編排卻造成更多的成本支出,本研究係依臺北市政府新建工程處福國路延伸工程(第1期)道路橋梁、共同管道及代辦自來水管線工程案件,共同管道箱涵構築協力廠商之機具派遣為研究範圍,利用線性規劃最佳化模式,求出人力、機具進場指派時間,提供決策者調度運籌之參考,以達最小成本為目標;依各參數之敏感度變化趨勢進行敏感度分析,藉此求得工區工作面需要之人力、機具之最少值,達成人力機具充分運用之目的。為驗證本模式合理性與實用性,以福國路延伸段為範例,進行模擬測試;並以最佳化模式所求得之派遣結果與一般人工經驗派遣進行比較,以驗證本研究最佳化模式產生的派遣結果,確實較人工經驗派遣更具效率且成本較低。故本研究可靈活運用於土方開挖與機具派遣檢討等規劃問題,幫助決策者精準規劃。
    ;Abstract
    In civil engineering, labor and machinery are usually dispatched by experience based on average allocation to maintain fairness. However, this manner of arrangement results in additional costs. Based on the machinery dispatch for the box culvert construction of the Road, Bridge, Common Channel, Tap Water Pipeline Project in the Fuguo Road Extension Project (Phase I) of the New Construction Office of the Taipei City Government, this study obtained the optimal labor and machinery entry time with the lineal planning optimization model for the reference of decision makers to perform logistics dispatch with the least cost. Sensitivity analysis was conducted based on the trend of parameter sensitivity change to obtain the minimum value of labor and machinery demand on the construction site to achieve full use of labor and machinery. To verify the reasonability and practicality of this model, a test was simulated on the Fuguo Road Extension Project.
    The outcomes were compared to the dispatch based on experience to verify the results of this optimization model. The comparison results showed that this model is more effective and cheaper than dispatch by experience. Therefore, this model can be applied to land excavation and machinery dispatch to help decision makers perform accurate planning.
    顯示於類別:[土木工程學系碩士在職專班] 博碩士論文

    文件中的檔案:

    檔案 描述 大小格式瀏覽次數
    index.html0KbHTML511檢視/開啟


    在NCUIR中所有的資料項目都受到原著作權保護.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明