    题名: 市地重劃工程規劃與執行障礙如何之 探討-以桃園經國市地重劃工程為例;Discussion on the project of planning urban land readjustment and the exclusion of implementation barriers- Take urban land readjustment project at Jingguo, Taoyuan City for example.
    作者: 吳昌駿;Wu,Chang-jun
    贡献者: 土木工程學系在職專班
    关键词: 市地重劃;拆遷補償;管線遷移;Urban Land Readjustment;Public Utilities;Urban Land Readjustment at Jingguo;Taoyuan City
    日期: 2015-07-24
    上传时间: 2015-09-23 10:05:17 (UTC+8)
    出版者: 國立中央大學
    摘要: 摘要
    目前公共工程執行上面臨高地價、高房價致用地取得不易,一但
    公共工程延遲將導致城市發展落後並且都市更新被迫暫緩,市地重劃
    可以創造政府、市民與土地所有權人三贏的局面,政府可以節省掉龐
    大的建設經費,市民可以享受公共建設與重劃公用設施的便利,土地
    所有權人也可享受重劃後環境品質提升與土地增值等實質利益,結合
    了民間財力與政府公權力以共同完成地方建設。係為未來解決公共建
    設用地問題及建設經費主流方式之一。
    藉由彙整現行公共工程履約管理規定中有關市地重劃的規劃及
    排除施工障礙之項目及對策,並以桃園市經國市地重劃區工程規劃與
    執行所遇到的施工障礙原因和解決對策,整理成案例加以分析棎討,
    研擬執行過程中各階段不確定因素發生之機率及處理標準作業流
    程,以提升工程執行效率。
    本研究結論,在辦理重劃區工程規劃與執行上所遇到的難題,主
    要聚焦在「用地取得」、「進場施作時機」、「既有管線遷移與銜接」、「施
    工界面協調」、「交通維持」及「公共設施點交」等項目,在規劃階段
    掌握蒐集前揭相關資訊,可完善做好重劃工程之規劃設計工作,減少
    施工階段因不完善之設計造成履約爭議及變更設計影響施工進度,使
    重劃工程執行順利。;Abstract
    Currently, implementation of public works is facing that market price
    of land is getting higher and higher. When government needs land to
    apply public projects, high land value will cause difficulty in obtaining
    land. Once the public projects cannot process, it will make development
    of urban area that fall behind schedule and urban renewal forced to
    postpone.
    Urban land readjustment can create a win-win-win situation for
    government, citizens and landowners. Urban land readjustment could save
    government a huge construction funds. For citizens, urban land
    readjustment can help them enjoy the convenience of public works and
    the benefits of readjustment of public utilities. The last win will belong to
    the landowner. After the urban land readjustment, the environment quality
    will improve a lot also land value will increase. Landowner can enjoy
    those substantial benefits.
    Urban land readjustment combined private financial support with
    government authority to complete local construction. To solve the
    problems in the usage of public construction and planning the budgets of
    construction, urban land readjustment will be one of the main streams to
    solve problems in the future.
    By arrange the entire existing compliance regulations of public
    works, we will coordinate the newest regulations about the planning of
    urban land readjustment and the countermeasures of encountered
    obstacles in construction. In this research, we will combine Jinguo,
    Taoyuan’s urban land readjustment ‘s case with the existing compliance
    regulations’ causes and solutions and organize information to a case and
    IV
    analyze it. In this research, we will imitate probability of occurrence in
    different stages and the standard process in order to enhance of efficiency
    in construction.
    Conclusions, when we are planning readjustment zone and execute
    the construction projects, we will face a lot of problems. This research
    will mainly focus on the problems that are "land acquisition,””when
    should we apply”” migration and convergence of existing pipeline",
    "interface of constructions", "traffic Control "and" public facility
    intercourse "etc.. To master collection of related information in the
    planning stage can improve the plan of readjustment project. Also we can
    reduce the changing and dispute of the construction that cause by the
    imperfect design during the construction stage. Those factors will affect
    the progress of the construction. To control all the factors will make
    readjustment construction go well.
    显示于类别:[土木工程學系碩士在職專班] 博碩士論文

    文件中的档案:

    档案 描述 大小格式浏览次数
    index.html0KbHTML732检视/开启


    在NCUIR中所有的数据项都受到原著作权保护.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明