中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/78950
English  |  正體中文  |  简体中文  |  Items with full text/Total items : 80990/80990 (100%)
Visitors : 41643879      Online Users : 1182
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
Scope Tips:
  • please add "double quotation mark" for query phrases to get precise results
  • please goto advance search for comprehansive author search
  • Adv. Search
    HomeLoginUploadHelpAboutAdminister Goto mobile version


    Please use this identifier to cite or link to this item: http://ir.lib.ncu.edu.tw/handle/987654321/78950


    Title: 結合BIM技術之時程延遲分析技術研發;Development of a Schedule Delay Analysis Approach Integrated with Bim Technique
    Authors: 楊智斌
    Contributors: 國立中央大學營建管理研究所
    Keywords: BIM;時程延遲分析;時程網圖;4D 模擬;BIM;Schedule Delay Analysis;Schedule Networks;4D Simulation
    Date: 2018-12-19
    Issue Date: 2018-12-20 14:20:49 (UTC+8)
    Publisher: 科技部
    Abstract: 時程延遲在營建工程專案經常出現,而致使時程延遲的履約爭議日益增加。同時使用規劃時 程網圖(as-planned schedule)及竣工時程網圖(as-built schedule)是國際上時程延遲分析方法的主 流,然而對於多數非時程管理專業的爭議處理人員而言,時程網圖的解讀與施工流程的掌握 有相當的困難度。隨著建築資訊模型(BIM)技術的快速發展,使得透過BIM 技術及4D 模擬, 提早發現施工可能問題以提升施工的整體效益已陸續被提出與實證,但結合時程延遲分析技 術的應用仍相當有限。本研究提出結合BIM 技術與時程延遲分析方法之創新作法,期待藉由 時程延遲分析技術與BIM 模型的整合,透過4D 模擬與視覺化的輔助,使時程爭議處理有關 人員能夠更清楚的掌握爭議的重點,有助於時程爭議的解決。 ;Schedule delays commonly appear in construction projects and result in schedule delay claims progressively. Advanced schedule delay analysis methods in the world commonly use as-planned schedule and as-built schedule to perform necessary analyses. However, most of professionals in delay claims have limited knowledge in deciphering schedule networks and construction processes. As Building Information Modeling (BIM) technique been quickly developed, using BIM and 4D simulation techniques have been proposed and implemented as well as achieving obvious benefits especially in identifying and solving constructability problems in advance. Obviously, researches that integrate BIM and schedule delay analysis techniques are rare and limited. This study targets on developing an innovative approach, which will integrate schedules delay analysis techniques and BIM models, to provide 4D simulation and visualization outcomes for professionals in schedule dispute resolution to identify schedule-related dispute problems easily and further to solve schedule-related disputes correctly.
    Relation: 財團法人國家實驗研究院科技政策研究與資訊中心
    Appears in Collections:[Graduate Institute of construction engineering] Research Project

    Files in This Item:

    File Description SizeFormat
    index.html0KbHTML316View/Open


    All items in NCUIR are protected by copyright, with all rights reserved.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明