中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/81792
English  |  正體中文  |  简体中文  |  全文笔数/总笔数 : 78937/78937 (100%)
造访人次 : 39156857      在线人数 : 667
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
搜寻范围 查询小技巧:
  • 您可在西文检索词汇前后加上"双引号",以获取较精准的检索结果
  • 若欲以作者姓名搜寻,建议至进阶搜寻限定作者字段,可获得较完整数据
  • 进阶搜寻


    jsp.display-item.identifier=請使用永久網址來引用或連結此文件: http://ir.lib.ncu.edu.tw/handle/987654321/81792


    题名: 國內工程工期爭議訴訟處理程序之研究;A Study on Resolution Processes of Construction
    作者: 温藝玲;Wen, I-Ling
    贡献者: 營建管理研究所在職專班
    关键词: 網圖;展延工期;要徑;浮時;Project Schedule;Extension of Time;Critical Path;Float Time
    日期: 2019-08-26
    上传时间: 2019-09-03 17:02:27 (UTC+8)
    出版者: 國立中央大學
    摘要: 與工期有關的爭議是國內工程爭議的主要類型,且因逾期完工所生爭議之案件,在法院的工程案件中亦佔有相當大的比例,但在爭議處理解決實務上,經常發生訴訟的利害關係人(包括當事人、代理人與法官等)無法清楚知道如何透過有系統且具證據力的程序,以解決營建工程與工期有關之爭議,故本研究之主要目的係藉由歸納分析法院判決認定工期展延之證據資料及過程。本研究透過文獻的整理以及實際案例的分析與佐證,提出「處理工期展延與否之分析流程」,透過此一流程圖,訴訟的利害關係人可以清楚知道如何透過有系統且具證據力的程序,進行有關工期爭議的處理,對於日後解決其面對的工期爭議事件,將能在品質上有所提升。經由本研究之進行,期盼可藉由研究成果對提昇工程實務界對定期更新工程網圖或工程預定進度表,以及於施工過程中保存爭議文件之重視,以利提升未來國內工程與工期有關的訴訟處理品質。;Duration-related dispute is the major type of construction disputes and the cases that completion duration is longer than contract duration are the majority of construction disputes cases in the court in Taiwan. However, the stakeholders, including party, agent and judge, in litigation cases usually do not really understand how to follow a systematical process and provide sufficient evidence in resolving a duration-related dispute. The purpose of this study is to analyze litigation cases to identify the processes and evidence for solving duration-related disputes. Through the approaches of literature review and case study, this study proposes a procedure to deal with extension-of-time dispute. With the procedure, the stakeholders in litigation cases can easily provide clear and convincing evidence. It is anticipated that the research outcomes provide a basic blueprint for how to resolve the disputes related to construction duration, and recognize the importance of updating project schedule and reserving documents related to the disputes. That is essential to improve the quality of duration-related disputes resolution.
    显示于类别:[營建管理研究所碩士在職專班] 博碩士論文

    文件中的档案:

    档案 描述 大小格式浏览次数
    index.html0KbHTML405检视/开启


    在NCUIR中所有的数据项都受到原著作权保护.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明