English  |  正體中文  |  简体中文  |  全文筆數/總筆數 : 80990/80990 (100%)
造訪人次 : 41625572      線上人數 : 1972
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
搜尋範圍 查詢小技巧:
  • 您可在西文檢索詞彙前後加上"雙引號",以獲取較精準的檢索結果
  • 若欲以作者姓名搜尋,建議至進階搜尋限定作者欄位,可獲得較完整資料
  • 進階搜尋


    請使用永久網址來引用或連結此文件: http://ir.lib.ncu.edu.tw/handle/987654321/88970


    題名: 公共工程履約爭議採爭議委員會機制之研究- 以桃園機場捷運機電系統統包工程為例;Construction contract dispute resolution using Dispute Review Board (DRB): A case study toward electrical and mechanical DB contract for Taoyuan airport MRT project
    作者: 戴詩宸;Tai, Shih-Chen
    貢獻者: 土木工程學系
    關鍵詞: 捷運工程;爭議委員會;機電統包工程;工程合約;履約爭議處理;MRT;Dispute Review Board (DRB);electrical and mechanical Design-Build;construction contract;dispute resolution
    日期: 2022-07-26
    上傳時間: 2022-10-04 10:45:41 (UTC+8)
    出版者: 國立中央大學
    摘要: 摘 要
    近年來捷運系統工程儼然成為台灣非常普遍之公共建設,目前亦有數個縣市區域型捷運系統刻正規劃或處於興建階段中,而捷運工程興建過程中容易因為許多外部宏觀或內部微觀的因素使得捷運工程履約爭議層出不窮且難以避免,因此如何有效的減少爭議案件數量或迅速解決爭議即為值得深入研究之課題。故本研究之主要目的為探討國際工程協會FIDIC契約之爭議審議委員會(Dispute Review Board, DRB)機制如何應用於國內捷運系統工程中以及應如何善用此機制之功能以減少或解決履約爭議。
    本研究首先透過文獻回顧探討了國內外設置爭議委員會之緣由與各種相關規定及辦法並將之進行比較與分析,挖掘出該機制仍存在著許多疑惑與運作困難之處。隨後本研究將此些問題利用專家訪談方法,訪談國內具有實務經驗之專家以強化此機制之缺陷與不足使其可更易發揮其效用並順利解決工程履約爭議,最後以桃園機場聯外捷運系統之機電系統統包工程作為案例以資驗證。
    從案例中得知採用此機制共順利解決86件履約爭議案,足證此機制之運作架構及功能是為有效解決工程履約爭議,雖然該案例最終仍有6件履約爭議案無法透過此機制解決,但藉由該機制仍有找到其他救濟方式,因而改採調解、仲裁及訴訟等履約爭議處理途徑。本研究最後得出國內採用此機制雖屬萌芽階段,但確為一個可供未來公共工程解決履約爭議之優先選擇,該機制具有許多優點,不僅可於履約過程中即刻解決問題,減少契約雙方消耗資源與時間,並能有效避免爭議不斷擴大而影響工進。;Abstract
    Massive Rapid Transit (MRT) has been popular in Taiwan and there are numerous regional MRT systems on going for the recent decades. Disputes are inevitable due to changes caused by the macro- and micro- economic statuses. The study objective is to discuss how the implementation of Dispute Review Board (DRB) on MRT cases functions using an empirical case of electrical and mechanical Design-Build (DB) contract for the Taoyuan airport MRT project. A comprehensive literature review has brought the overview for the common methods in dispute resolution and led to the questions for expert interviews. The expertise summary supports a DRB mechanism that constructs the framework for empirical practices. The case study, electrical and mechanical DB contract for Taoyuan airport MRT project, involves 86 disputes, showing that the proposed framework functions well for dispute settlement. Only 6 of which require further resolution such as litigation or arbitration. The proposed mechanism significantly reduced the amount of severe disputes that may consume more resources and time to settle.
    顯示於類別:[土木工程研究所] 博碩士論文

    文件中的檔案:

    檔案 描述 大小格式瀏覽次數
    index.html0KbHTML33檢視/開啟


    在NCUIR中所有的資料項目都受到原著作權保護.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明