中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/73070
English  |  正體中文  |  简体中文  |  Items with full text/Total items : 80990/80990 (100%)
Visitors : 41643035      Online Users : 1359
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
Scope Tips:
  • please add "double quotation mark" for query phrases to get precise results
  • please goto advance search for comprehansive author search
  • Adv. Search
    HomeLoginUploadHelpAboutAdminister Goto mobile version


    Please use this identifier to cite or link to this item: http://ir.lib.ncu.edu.tw/handle/987654321/73070


    Title: 運用關聯法則探討預鑄構件生產派工之研究;Exploring association rules of work activities for producing precast components in Taiwan construction industry.
    Authors: 吳宗瑋;Wu, Zong-Wei
    Contributors: 營建管理研究所
    Keywords: 預鑄構件;關聯法則;相關性;生產工項;precast component;association rule;correlation;construction activity
    Date: 2017-01-20
    Issue Date: 2017-05-05 17:43:08 (UTC+8)
    Publisher: 國立中央大學
    Abstract: 台灣的營建產業中,預鑄構件的生產是屬於高度勞工密集且經驗導向的產業,本研究的研究目的是找出預鑄構件生產工項間的關聯法則,以得到工班調度和勞動成本最適化的結果。透過全面性的文獻回顧,本研究所收集的數據資料為全台灣近十年來的預鑄構件專案的生產時間,並花費數個月的時間建立資料庫,其中包括大樑、小樑、柱這三種主要的建築構件,每個構件包含14個生產工項,且分別有19558根大樑、16731根小樑以及18854根柱。本研究運用Pearson相關係數法確立工項和工項間的相關性,也運用了Apriori演算法,其中置信度的參數設定為90%,而支持度的參數設定為15%。本研究的第一個結論發現有四個生產工項並不需要高度技術工班,包含混凝土澆置、混凝土養護、脫模以及存放入庫,第二個結論發現,在大樑的工項中,放樣對其他生產工項有顯著性的影響,而在小樑和柱當中,則是預埋件埋設對其他工項有顯著性的影響,以上結論在工班調度以及勞動成本的最適化提供了明確的方向。;Manufacturing precast components in the Taiwan construction industry is a highly labor-intensive and experience-oriented process. The research objective is to explore the association rules among all precast activities in order that work scheduling and cost can be optimal. Gathering information from a comprehensive literature review, we aim at the entire precast production data for the data collection in Taiwan in the recent decade and it takes months to establish the database including three major components of pillar, large beam, and small beam. Each component contains 14 work activities and there are 18,854, 19,558, and 16,731 components for pillar, large beam, and small beam, respectively. We carry out the Pearson correlation analysis to determine the relationship among the activities, and adopt the Apriori algorithm with the parameter settings of confidence level at 90% and support value at 15%. The first finding indicates that 4 activities do not need to require high-skilled workers including pouring concrete, maintaining concrete, stripping module, and sending to inventory. The other finding points out that the layout activity significantly influences other activities for large beams; item pre-installation significantly influences other activities for both small beams and pillars. The findings provide a clear way for optimizing work shifts and labor costs.
    Appears in Collections:[Graduate Institute of construction engineering] Electronic Thesis & Dissertation

    Files in This Item:

    File Description SizeFormat
    index.html0KbHTML418View/Open


    All items in NCUIR are protected by copyright, with all rights reserved.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明