中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/76313
English  |  正體中文  |  简体中文  |  Items with full text/Total items : 81570/81570 (100%)
Visitors : 47116627      Online Users : 600
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
Scope Tips:
  • please add "double quotation mark" for query phrases to get precise results
  • please goto advance search for comprehansive author search
  • Adv. Search
    HomeLoginUploadHelpAboutAdminister Goto mobile version


    Please use this identifier to cite or link to this item: http://ir.lib.ncu.edu.tw/handle/987654321/76313


    Title: 結合BIM技術之時程延遲分析技術研發;Development of a Schedule Delay Analysis Approach Integrated with Bim Technique
    Authors: 楊智斌
    Contributors: 國立中央大學營建管理研究所
    Keywords: 土木水利工程;BIM;時程延遲分析;時程網圖;4D 模擬;BIM;Schedule Delay Analysis;Schedule Networks;4D Simulation
    Date: 2018-08-01
    Issue Date: 2018-05-02 17:34:40 (UTC+8)
    Publisher: 科技部
    Abstract: 時程延遲在營建工程專案經常出現,而致使時程延遲的履約爭議日益增加。同時使用規劃時程網圖(as-planned schedule)及竣工時程網圖(as-built schedule)是國際上時程延遲分析方法的主流,然而對於多數非時程管理專業的爭議處理人員而言,時程網圖的解讀與施工流程的掌握有相當的困難度。隨著建築資訊模型(BIM)技術的快速發展,使得透過BIM 技術及4D 模擬,提早發現施工可能問題以提升施工的整體效益已陸續被提出與實證,但結合時程延遲分析技術的應用仍相當有限。本研究提出結合BIM 技術與時程延遲分析方法之創新作法,期待藉由時程延遲分析技術與BIM 模型的整合,透過4D 模擬與視覺化的輔助,使時程爭議處理有關人員能夠更清楚的掌握爭議的重點,有助於時程爭議的解決。
    Relation: 財團法人國家實驗研究院科技政策研究與資訊中心
    Appears in Collections:[Graduate Institute of construction engineering] Research Project

    Files in This Item:

    File Description SizeFormat
    index.html0KbHTML377View/Open


    All items in NCUIR are protected by copyright, with all rights reserved.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明