中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/95946
English  |  正體中文  |  简体中文  |  Items with full text/Total items : 80990/80990 (100%)
Visitors : 43256409      Online Users : 712
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
Scope Tips:
  • please add "double quotation mark" for query phrases to get precise results
  • please goto advance search for comprehansive author search
  • Adv. Search
    HomeLoginUploadHelpAboutAdminister Goto mobile version


    Please use this identifier to cite or link to this item: http://ir.lib.ncu.edu.tw/handle/987654321/95946


    Title: 營建工程工作物先行使用權責歸屬之研究
    Authors: 季翔渝;Chi, Hsiang-Yu
    Contributors: 土木系營建管理碩士班
    Keywords: 瑕疵爭議;危險責任歸屬;先行使用;Defect dispute;Liability of dangerous Activity;Using facilities before acceptance
    Date: 2024-06-28
    Issue Date: 2024-10-09 17:26:01 (UTC+8)
    Publisher: 國立中央大學
    Abstract: 在現行實務狀況下,工程案件須經過竣工、驗收、交付三個主要流程,定作人方能依此取得工作物使用之權利,然為因應定作人使用之需求,如:政策需求、協調其他廠商工程施作。定作人在一定情況下,仍然能保有未完成驗收卻先行使用或部分驗收使用之權利。參照政府採購法、政府採購法施行細則、工程契約範本中,皆有在驗收的項目之中提及如需先行使用,應先經過部分驗收或完全驗收,業主才能夠取得定作物的部分或全部使用權利,但相關條文中並未有細節性的規定,且有時會發生雙方並未事前約定之狀況,現階段對此種情況之處理,除了訴訟外,沒有其他更為便捷的處理流程,但由
    於先行使用而衍生出關於危險責任、權利義務、保險關係等問題,有時又具有緊急性,訴訟途徑不但曠日廢時,也會耗費大量司法資源,故本研究欲透過司法案例判決、現行實務觀點及專家訪談之方式,期能尋找出關於先行使用的固定處理流程或責任歸屬,作為日後訂立相關法規之依據。;In civil construction projects, project cases must go through three main processes: completion, acceptance and delivery before the ordering party can obtain the right to use the work. However, due to policy requirements and other demand considerations, the ordering party can still retain the right to use the work before the acceptance is completed. The right touse or partially accept the use. In the regulations, it is mentioned that if the ordering party needs to use it first, they need to pass the acceptance, then they can obtain the right to use the ordered crop. Sometimes, there are no detailed provisions in the law, and situations without prior agreement often occur, leading to litigation. However, due to the derived issues about
    responsibilities, rights and obligations, etc., they are sometimes urgent and time may not be sufficient. Therefore the study aims to clarify the disputes, processingprocedures and responsibilities regarding prior use.
    Appears in Collections:[Graduate Institute of construction engineering] Electronic Thesis & Dissertation

    Files in This Item:

    File Description SizeFormat
    index.html0KbHTML40View/Open


    All items in NCUIR are protected by copyright, with all rights reserved.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明