摘要: The purpose of this study is to develop a systematic scheduling model that will help ready mixed concrete (RMC) carriers/suppliers with effective scheduling adjustment after temporary breakdown of mixers under stochastic travel times. The model is formulated as a mixed integer network flow problem with side constraints that is characterized as NP-hard. The authors employ problem decomposition and relaxation techniques, with a mathematical programing solver, to develop an algorithm that is capable of efficiently solving the problem. A simulation-based evaluation method is also proposed to evaluate the model, joined with a deterministic model, as well as the method currently used in actual operations. Finally, a case study is performed using real operating data from a Taiwan RMC firm. The preliminary results demonstrate that the stochastic model and the solution algorithm could be useful to reduce system cost for the RMC carrier in actual operations. 出版者: Taylor & Francis 出版日期: 2016-10-19 出處: Transportation letters, 2016-10, Vol.8 (5), p.286-300 版權: 2016 Informa UK Limited, trading as Taylor & Francis Group 2016 識別號: ISSN: 1942-7867 識別號: EISSN: 1942-7875 識別號: DOI: 10.1080/19427867.2016.1188522