dc.description.abstract | The public tenders of joint venture are wildly used in public constructions, according to the Government E-procurement system, joint venture took 43% of the total award of bid, and the amounts were up to 52% of the total award of bid values between 2010 and 2014. However, the most of joint venture contractors were asked/forced by proprietor in the bidding stage for signing the joint venture agreements which become the execution references of the contractors after the award of bid, the perception gaps between the joint venture contractors always exist since the beginning of the project planning, without consensus leads to controversy, joint venture will become the empty talk.
The research via the references at home and abroad, which are about execution systems of joint venture, governance modes, factors of influence and keys to success or failure, to investigate the issues from definition of joint venture, organizations styles and operational execution, the aspects of regulations, the interface between contractors, etc., and to analyze the cooperation pattern between civil contractors and E&M contractors, which were joint venture in the case of “Taipei Railway Workshop Relocation Program, Fugan Depot”, to investigate “The difficulties of executing the joint venture agreements between the public construction contractors by now”, “To propose recommendations about the main articles of joint venture agreements, which related to the rights and duties”, “In order to prevent the controversies, to propose the matters need to be aware when the joint ventures working on the constructions.”, etc., for research purpose.
This research discovered:
1. The contractor delegate which is assigned by the joint venture agreements for the project executing, not just the only contractor with the proprietors. The every member of the joint venture should sign the contract with proprietors or organizations in accordance with the equal beneficial results of legal aspect.
2. Joint venture agreement applies the bidding stage only. Contractors need to refer to the joint venture agreement while the contract is making after award of bid, the contracts includes the duty of each member and the contract price should be listed, and must not transgress the contract.
3. To compose the DRB system is necessary, and the organization structure and weight need to be balanced. There benefits from the meeting discussions are timeliness and the highest decision making, and all members should go along with the conclusion of the meeting. And propose suggestions which could have the further discussion, implement the effective of joint venture between contractors.
| en_US |