摘要(英) |
The textile industry in Taiwan has been progressing in the past 60 years; however, the fabric manufacturer has challenged dyeing factories for delaying the manufacturing process most of the time. This study attempts to identify the challenges that a dyeing factory has on manufacturing scheduling. Advanced Planning & Scheduling System (APS) is a scheduling system that can compute multiple factors to improve manufacturing efficiency. This study will evaluate the feasibility of adopting an APS to overcome the challenges.
The research applies Leavitt’s Diamond Model and conducts a case study to identify the case company’s organizational structure, people’s responsibility, the manufacturing and the operating processes, the system-implementation history, the current scheduling logic that the company applies. The study also evaluates whether or not the current technology infrastructure can support the demand. Furthermore, the study further investigates if the APS is able to resolve the delay problem that the dyeing factory currently has, for helping the company make a solid decision on APS adoption.
The results lead to several major findings. First, the delay problem the company is suffering has been caused by the insufficient capacity, and the remake has further over-loaded the capacity, leading to a vicious circle of delaying. The infrastructure and the database of the company are insufficient for automatically judge the color order depending on the depth, so it is not quite feasible for the company to adopt an APS currently. Instead, the company should build up more data basis, and further analyze the relationship between remake and various manufacturing factors that might interfere the scheduling.
In the future, only when the infrastructure construction of information flow has been setup, can the scheduling be computed by simulation techniques, and the manager can do a relative more solid decision than before. |
參考文獻 |
【英文文獻】
1. Bidanda, B. & Cleland, D. I. (1989), “Techniques to assess project feasibility,” Project Management Journal, 20(2), 5-10.
2. Davis, G.B., and Olson, M.H., (1985), Management Information Systems: A Conceptual Foundation, Structure and Development (2nd ed). New York: McGraw-Hill Inc.
3. Hammer, M. (1993), Reengineering the Corporation. New York: Harper Collins.
4. Inside Nike′s plan to cut lead times from 60 days to 10, “SUPPLY CHAIN DIVE,” (accessd 2018/03/30, available at : https://www.supplychaindive.com/news/nike-lead-times-innovation-automation-consumer/508606/)
5. Leavitt, H. J. (1964), Managerial Psychology. Chicago: The University of Chicago Press, Ltd.
6. Pinedo, M. L. (2016), Scheduling: Theory, Algorithms, and Systems (5th ed). New York: Springer.
7. Parunak, V. D. (1991), “Characterizing the manufacturing scheduling problem,” Journal of Manufacturing Systems, 10(3), 241-259.
8. Pettigrew, A.M. (1985), The Awakening Giant: Continuity and Change in ICI. Oxford: Blackwell.
9. Pettigrew, A.M. (1987), “Context and action in the transformation of the firm,” Journal of Management Studies, 24(6), 649-670.
10. Pettigrew, A.M. (1990), “Longitudinal field research on change: Theory and practice,” Organization Science, 1(3), 297-292.
11. Premkumar, G. & Ramamurthy, K. & Crum, M. (1997), “Determinants of EDI adoption in the transportation industry,” European Journal of Information System, 6(2), 107-201.
12. Robey, D., (1987), “Implementation and the Organizational Impacts of Information System,” Interface, 17(3), 72-84.
13. Saydam, Cem & Cooper, W. D. (2002), “A decision support system for scheduling jobs on multi‐port dyeing machines,” International Journal of Operations & Production Management, 22(9), 1054-1065.
14. Scheduling, “Techopedia,” (accessd 2018/2/20, available at : https://www.techopedia.com/definition/9654/scheduling)
15. Serafeimidis, V. & Smithson, S. (1996), “The management of change for information systems evaluation practice: Experience form a case study,” International Journal of Information Management, 16(3), 205-217.
16. Supply management: A complex function, “Ukessays,” (accessd 2018/3/30, available at: https://www.ukessays.com/essays/management/a-complex-function.php)
17. Technical Textile Market worth 220.37 Billion USD by 2022, “MARKETS AND MARKETS,” (accessd 2018/5/20, available at: https://www.marketsandmarkets.com/PressReleases/technical-textile.asp)
【中文文獻】
1. 王本正、林余任(2003),「企業導入ERP之變革管理—以A企業為例」,電子商務研究,第1卷,第2期,185-202。
2. 王立志(1999),系統化運籌與供應鏈管理。台中:滄海出版社
3. 王立志、林獻琨(2007),「應用於成品布紡織業的整合性生產規劃與排程模式」,紡織綜合研究期刊,第17卷,第1期,1-14。
4. 伍虹儒(2016),生產與運作管理。四川:西南財經大學出版社。
5. 宋茂林(2002),「由行業別ERP到供應鏈ERP:焦點差異化策略之應用」,國立中山大學資訊管理研究所所學位論文。
6. 我國紡織品出進口統計(2018),「紡拓會全球資訊網」,http://news.textiles.org.tw/ie/IEStatistics.aspx,存取時間:2018/2/24。
7. 林東清(2002),組織引進IT的互動性架構,資訊管理E化企業的核心競爭能力。台北市:智勝文化事業有限公司。
8. 周淑卿、汪志勇(2004),「以五力分析方法評估企業導入ERP系統之效益」,產業論壇,第6卷,第3期,65-92。
9. 邱敬琮(2006),「先進規劃與排程系統應用於紡織業之研究」,東海大學工業工程與經營學研究所學位論文。
10. 陳小芬、王存國(2005),「企業資源規劃系統的導入:從脈絡論分析個案研究」,中山管理評論,第13卷,第1期,217-245。
11. 陳瑩芝(1999),「多工段基因導向派工法則之研究」,國立交通大學工業工程與管理學研究所學位論文。
12. 黃俊豪(2009),「運用於紡織廠中具平行機台染整製程之啟發式排程演算法」,東海大學工業工程與經營學研究所學位論文。
13. 楊啟瑞(1999),「紡織業多階層製造系統之派工法則研究」,國立交通大學工業工程與管理學研究所學位論文。
14. 經理人月刊編輯部(2007),「資訊管理」,https://www.managertoday.com.tw/articles/view/821,存取時間:2018/2/12。
15. 葉麗芬(2002),「雙目標非等效平行機台排程問題之探討」,元智大學工業工程與管理學系學位論文。
16. 鄭勇志(2012),「生產排程規劃-不可或缺的管理決策工具」,https://mymkc.com/article/content/21287,存取時間:2018/3/17。
17. 蕭瑞麟(2018),「為什麼導入資訊系統常常失敗?經營者該懂的思考邏輯」,https://www.managertoday.com.tw/columns/view/55844,存取時間:2018/3/24。
18. 賴奕茵(2008),「紡織廠染整段生產排程問題之研究」,東海大學工業工程與經營學研究所學位論文。 |