中大機構典藏-NCU Institutional Repository-提供博碩士論文、考古題、期刊論文、研究計畫等下載:Item 987654321/64937
English  |  正體中文  |  简体中文  |  Items with full text/Total items : 78852/78852 (100%)
Visitors : 38272342      Online Users : 498
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
Scope Tips:
  • please add "double quotation mark" for query phrases to get precise results
  • please goto advance search for comprehansive author search
  • Adv. Search
    HomeLoginUploadHelpAboutAdminister Goto mobile version


    Please use this identifier to cite or link to this item: http://ir.lib.ncu.edu.tw/handle/987654321/64937


    Title: 雙機台間不具有儲存空間下極小化總延遲時間之流程式生產排程問題;Two-Machine Flow Shop Scheduling Problem with Blocking for Minimizing Total Tardiness
    Authors: 鍾承叡;Jhong,Cheng-Ruei
    Contributors: 工業管理研究所
    Keywords: 雙機台流程式生產排程;總延遲時間;不具儲存空間;Two-machine;Flow shop;Blocking;Total tardiness
    Date: 2014-07-28
    Issue Date: 2014-10-15 14:34:46 (UTC+8)
    Publisher: 國立中央大學
    Abstract: 本研究探討雙機台間不具有儲存空間下極小化總延遲時間之雙機流程式生產排程問題。此篇我們假設有2台機台和n個工作,每個工作在兩機台分別有不同的工作時間以及交期時間,每個工作的釋放時間都相同,而工作的順序在進入機台1後就決定。如果工作在機台1完成後而機台2尚有未完成的工作,此時在機台1完成的工作將會被鎖在機台1,這將會使交期時間增加。
    本文針對不具有儲存空間的雙機台排程問題所造成的延遲時間增加,提出5個定理來決定工作在最佳解排程下的的順序以及一個下限的方法來決定分支的方向,最後運用在分支界限法求得n個工作之最佳工作順序,使得總延遲時間為最小。在實驗分析裡我們先用相似的期刊論文驗證演算法的正確性。接下來我們比較Ronconi and Armentano (2001) 這篇論文在雙機台情境下的結果,我們得到了在工作數介於10至18之間我們的平均時間與平均產生的節點數都較Ronconi and Armentano (2001) 這篇論文來的有效率。
    ;This paper considers a flow shop scheduling problem with blocking where the objective is to minimize total tardiness. There are two machines and n jobs, each job has different due date and the sequence of job is decided by machine 1. In two-machine flow shop with blocking scheduled problem, there are zero capacity buffer between machines and the job of completing is block on machine until the next downstream machine is available. The total tardiness will increase by influence of blocking constraint. We use branch and bound algorithm to find out an optimal sequence and propose five dominance criteria which are decide jobs of the precedence in an optimal schedule. For bounding, we extend lower bound of Pan, Chen and Chao (2002) to improve the branch and bound algorithm. In computation experiment, we use four scenarios of Ronconi and Armentano (2001) to test our algorithm. In job size between 10 and 18, our algorithm branches out fewer number of nodes as compared to the result in Ronconi and Armentano (2001).
    Appears in Collections:[Graduate Institute of Industrial Management] Electronic Thesis & Dissertation

    Files in This Item:

    File Description SizeFormat
    index.html0KbHTML642View/Open


    All items in NCUIR are protected by copyright, with all rights reserved.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明