    题名: 國內時程網圖健康度評估指標建立之研究;A Study on Developing Evaluation Indicators for Construction Schedule Network Health
    作者: 劉亮君;Liu, Liang-Chun
    贡献者: 土木系營建管理碩士班
    关键词: 營建工程;時程網圖;基準時程;網圖審查指標;網圖健康度
    日期: 2022-01-24
    上传时间: 2022-07-14 01:23:17 (UTC+8)
    出版者: 國立中央大學
    摘要: 國內工程進度出現延誤之情形層出不窮,規劃正確及合理的時程網圖對於工程能否順利進行有著很大的影響。當工程發生爭議時,已通過審查的時程網圖往往是爭議處理的重要判斷依據。一個專案是否能順利進行,與時程網圖的品質與控管有著密不可分的關係。然而國內對於時程網圖的審查標準四散各處,且各機關相關作業手冊往往僅有原則性的審查建議,審查人員在審查時常常無所適從,只能憑自身經驗進行判斷,導致國內的時程網圖審查常常流於形式、成效不佳。本研究以文獻回顧的方式,綜整國外對於時程網圖健康度之概念與建議,結合國內時程網圖相關文獻建立的網圖審查流程及準則,進而建立合適的時程網圖評估指標。本研究最終彙整出九大網圖健康度評估指標與60個檢核細項,以初步評判網圖之完整性、正確性及合理性。本研究另以實際工程案例之時程網圖進行分析,檢視其指標之可行性,並透過訪談評估是否適用於工程實務中。期望本研究之成果可以彌補國內審查標準不足之現況,並能提升國內時程網圖之水準。;Delays in the construction processes of domestic projects emerge endlessly, and a correct and reasonable construction schedule has a great impact on the smooth progress of the project. When a dispute occurs in a project, the construction schedule that has passed the review is often the important basis for reaching the dispute settlement. Whether a project can proceed smoothly is inseparable from the quality and control of the construction schedule. However, the domestic review standards for construction schedule are unclear, and the relevant execution manuals for schedule review by various government agencies commonly have general and limited review recommendations. The reviewers are often at a loss when reviewing, and can only make judgments based on their own experience. As a result, domestic construction schedule reviews often become mere formalities and review outcomes are poorly effective for improving the performance of construction schedule. This study used a literature review method to extract the concepts and suggestions on the health of construction schedule from other countries, combined them with the schedule network review process and criteria established by domestic research outcomes and government execution manuals, and established appropriate schedule network evaluation indicators. In the end, nine major construction schedule health evaluation indicators consisting of 60 evaluation items were developed to evaluate the completeness, correctness and rationality of construction schedule based on the purpose of preliminary schedule review. This study has confirmed the feasibility of proposed evaluation indicators by actual construction schedule network, and their appropriateness by domain expert interviews. Excluding to make up for the current lack of domestic review standards, it is hoped that the performance level of domestic construction schedule can be improved based on the outcomes of this study.
    显示于类别:[營建管理研究所 ] 博碩士論文

    文件中的档案:

    档案 描述 大小格式浏览次数
    index.html0KbHTML144检视/开启


    在NCUIR中所有的数据项都受到原著作权保护.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明