English
| 正體中文 |
简体中文
|
全文筆數/總筆數 : 94201/94201 (100%)
造訪人次 : 81663423 線上人數 : 4049
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by
NTU Library IR team.
搜尋範圍
全部NCUIR
工學院
土木工程學系
--期刊論文
查詢小技巧:
您可在西文檢索詞彙前後加上"雙引號",以獲取較精準的檢索結果
若欲以作者姓名搜尋,建議至進階搜尋限定作者欄位,可獲得較完整資料
進階搜尋
主頁
‧
登入
‧
上傳
‧
說明
‧
關於NCUIR
‧
管理
NCU Institutional Repository
>
工學院
>
土木工程學系
>
期刊論文
>
Item 987654321/100043
資料載入中.....
書目資料匯出
Endnote RIS 格式資料匯出
Bibtex 格式資料匯出
引文資訊
資料載入中.....
資料載入中.....
請使用永久網址來引用或連結此文件:
https://ir.lib.ncu.edu.tw/handle/987654321/100043
題名:
Incorporating lost productivity calculation into delay analysis for construction projects
作者:
楊智斌
;
Yang, Jyh-Bin
;
Huang, Kuei-Mei
;
Lee, Chang-Hung
;
Chiu, Chui-Te
貢獻者:
工學院土木工程學系
關鍵詞:
Analysis
;
Civil Engineering
;
Construction
;
Construction industry
;
Construction Management
;
construction projects
;
Contractors
;
Delay
;
delay analysis
;
delay claim
;
Engineering
;
Geotechnical Engineering & Applied Earth Sciences
;
Impact analysis
;
Industrial Pollution Prevention
;
lost productivity
;
Mathematical analysis
;
Productivity
;
Project engineering
;
schedule management
;
Schedules
;
토목공학
日期:
2014-03-01
上傳時間:
2026-04-21 13:46:21 (UTC+8)
出版者:
Korean Society of Civil Engineers;Berlin/Heidelberg: Elsevier Inc
摘要:
摘要: Schedule delays commonly occur in construction projects and often result in delay claims. Several studies have proposed different schedule delay analysis methodologies. By using as-planned and as-built schedules, most previous studies have concentrated on calculating the impact of identified delay events on project duration but have neglected to connect impact calculation from detailed delay evidence in their analyses. Lost productivity, which is a primary cause of schedule delays, entails the completion of work at less than the planned rate of production; it is usually experienced by contractors. To solve analysis problem of schedule delays associated with lost productivity, this study proposes a delay analysis method (the LOPE method) that integrates a lost productivity calculation approach and a well-known schedule delay analysis method, the collapsed as-built method. As demonstrated through a simplified case study, the proposed method is beneficial for calculating the impacts of schedule delays caused by lost productivity.
其他題名: KSCE J Civ Eng
出版者: Berlin/Heidelberg: Elsevier Inc
出版日期: 2014-03
出處: KSCE Journal of Civil Engineering, 2014, 18(2), , pp.380-388
資源來源: Alma/SFX Local Collection
版權: 2014 © Korean Society of Civil Engineers and Springer-Verlag Berlin Heidelberg 2014 published by Elsevier inc.
版權: Korean Society of Civil Engineers and Springer-Verlag Berlin Heidelberg 2014
版權: Korean Society of Civil Engineers and Springer-Verlag Berlin Heidelberg 2014.
識別號: ISSN: 1226-7988
識別號: EISSN: 1976-3808
識別號: DOI: 10.1007/s12205-014-0128-8
顯示於類別:
[土木工程學系 ] 期刊論文
文件中的檔案:
檔案
描述
大小
格式
瀏覽次數
index.html
0Kb
HTML
9
檢視/開啟
在NCUIR中所有的資料項目都受到原著作權保護.
社群 sharing
::: Copyright National Central University. | 國立中央大學圖書館版權所有 |
收藏本站
|
設為首頁
| 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
DSpace Software
Copyright © 2002-2004
MIT
&
Hewlett-Packard
/
Enhanced by
NTU Library IR team
Copyright ©
-
隱私權政策聲明