English  |  正體中文  |  简体中文  |  全文筆數/總筆數 : 78818/78818 (100%)
造訪人次 : 34642389      線上人數 : 353
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library IR team.
搜尋範圍 查詢小技巧:
  • 您可在西文檢索詞彙前後加上"雙引號",以獲取較精準的檢索結果
  • 若欲以作者姓名搜尋,建議至進階搜尋限定作者欄位,可獲得較完整資料
  • 進階搜尋


    請使用永久網址來引用或連結此文件: http://ir.lib.ncu.edu.tw/handle/987654321/85574


    題名: Analyzing Early Termination and Transfer of BOT Infrastructure Projects in Taiwan;Analyzing Early Termination and Transfer of BOT Infrastructure Projects in Taiwan
    作者: 王暐翔;Wang, Wei-Hsiang
    貢獻者: 土木系營建管理碩士班
    關鍵詞: BOT;移轉階段;契約範本;促參法;BOT;Transfer;Contract Template;Rule of Act for Promotion of Private Participation in Infrastructure Project
    日期: 2021-03-16
    上傳時間: 2021-12-07 10:59:53 (UTC+8)
    出版者: 國立中央大學
    摘要: 建造-運營-移轉(BOT)是一種政府把要新蓋的公共建設,交給民間出資興建及經營一段時間後,再將所有權移轉政府的模式,民間機構從主辦機關獲得特許權,得以參與透過投資公共基礎設施提供各種社會所需之服務。關於BOT案件的進程,有幾個重要的里程碑,包括:1.主辦機關向民間機構提供土地特許權; 2.建設階段,通常是以統包工程或設計建造的形式; 3.測試並運營已建成的設施,並4.將已建成的設施和土地特許權移轉回主辦機關。
    在這些里程碑中,在移轉這個里程碑中,對兩造而言,可能此里程碑包含著多方面的風險。兩造都知道,這是兩造於法律關係上分開的里程碑,因此,所有相關事宜都必須在法律關係正式分開前得到處理和決定。然而,在接近運營的最後階段時,在兩造之間將會進行一系列的鬥爭或競爭性質的現象。
    可以肯定的是,大多數在期前終止的BOT項目中的參與者不僅處於敵對狀態,而且他們也沒有足夠的時間來處理此事件。但是,基於互惠互利的原則,本研究將移轉失敗定義為無法成功解決紛爭之結果。本研究旨在詳細研究失敗的期前終止BOT案件的轉移。而且,本研究將試圖制定出更好的指南,而本研究所參照指南最初是由財政部促參司委託臺灣世曦工程顧問公司提出的。本研究亦推出具有良好監督系統的BOT契約範本,以供未來主辦機關以及民間機構有一更和諧且能預防移轉失敗之契約條款。
    ;Build-Operate-Transfer (BOT) is a project delivery model that a private institution receives a concession from the authority in charge to participate in providing various social functions by public infrastructure investment. There are several key milestones concerning the progress of a BOT project, including: 1. the authority in charge’s offer of land concession to the private institution; 2.the construction stage, often in the form of turnkey or design-build; 3. the commissioning of operation of the built facility, and 4. the transfer of built facility and land concession to the authority in charge.
    Among these milestones, the transfer milestone perhaps involves most aspects of risks to the parties. Parties are aware that this is the milestone in which the parties depart from each other legally, thus all matters concerned will have to be dealt with and finalized before legal severance. This creates a vast “game” series between the party when approaching the final stage of operation.
    Granted the fact that, parties in most early-terminated BOT projects are not only in a hostile situation but also they will not have sufficient time to encounter the incident. Yet, based on the principle of mutual benefit, transfer failure is defined as when the disputes could not be solved by the parties in this study. This work aims to investigate failed early-termination BOT project transfer in detail. What’s more, this work also attempts to develop a better guideline, which is originally proposed by CECI, and the template of BOT project contract with a good supervising system, to allow the authority in charge and the private institution in BOT projects to have harmonic proposals for transfer contract terms.
    顯示於類別:[營建管理研究所 ] 博碩士論文

    文件中的檔案:

    檔案 描述 大小格式瀏覽次數
    index.html0KbHTML136檢視/開啟


    在NCUIR中所有的資料項目都受到原著作權保護.

    社群 sharing

    ::: Copyright National Central University. | 國立中央大學圖書館版權所有 | 收藏本站 | 設為首頁 | 最佳瀏覽畫面: 1024*768 | 建站日期:8-24-2009 :::
    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library IR team Copyright ©   - 隱私權政策聲明