摘要: Assessing schedule delay's impact on total project duration to distribute delay liability remains a controversy. None of existing delay analysis methods is perfect because including an element of assumptions, subjective assessment and theoretical projection. Windows-based delay analysis methods are excellent in identifying and measuring construction schedule delays. Based on a previous study identifying potential problems in available windows-based delay analysis methods, this study proposes an innovative windows-based delay analysis method, called the effect-based delay analysis method (the EDAM method). The EDAM method performs delay analysis using extracted windows and determines delay impacts by considering the effects of delays on the critical path(s). According to its application to hypothetical cases and comparisons with other methods, the EDAM method is efficient in delay analysis and effective in solving concurrent delays and determining schedule shortened. The proposed EDAM method is a good alternative for schedule delay analysis for construction projects. ► EDAM method considers critical path effects in delay analysis. ► EDAM method has a systematic approach for delay analysis stably and efficiently. ► EDAM method is effective in determining concurrent delays and schedule shortened. ► EDAM method has an approach for liability distribution in concurrent delays. 出版者: Kidlington: Elsevier Ltd 出版日期: 2012-04-01 出處: International journal of project management, 2012-04, Vol.30 (3), p.385-397 資源來源: Elsevier ScienceDirect Journals Complete 版權: 2011 Elsevier Ltd and IPMA 版權: Copyright Elsevier Science Ltd. Apr 2012 識別號: ISSN: 0263-7863 識別號: EISSN: 1873-4634 識別號: DOI: 10.1016/j.ijproman.2011.06.003